Construction Update October 2024
Award-winning Independent Whisky
Bankfoot Farm, Inverkip, PA16 0DT
2024October 2024 Update: Major Installation Milestone. October marked a transformative month at Ardgowan Distillery as we moved from construction to complex installation work, bringing us significantly closer to operational status.
Major Equipment Installation
A major milestone was reached with the successful placement of all major vessels on site. The malt bins are now erected, and we’ve begun the intricate work of installing elevators, milling equipment, and the grist case. What began as technical drawings is now taking physical form before our eyes.
The Scale of Our Operation
The sheer scale of our installation work is impressive, with an extensive network of components being integrated:
– 4,138 meters of pipework
– 5,548 meters of cabling
– 517 valves
– 20 pumps
– 292 instruments
– 8 heat exchangers
– 2,081 fittings
– 1,164 flanges & clamps
Each of these components must be precisely installed and thoroughly tested before we can begin operations. It’s a testament to the complexity and precision required in modern distillery construction.
Team Effort
October saw our site bustling with activity, with over 60 contractors working simultaneously to bring the Ardgowan dream to life. The coordination and expertise required to manage this phase of the project cannot be understated.
Looking Ahead
While significant progress has been made, we’re eagerly anticipating the arrival of our copper stills in early November – the heart of any distillery. This final major component will mark another exciting milestone in our journey.
—
*Stay tuned for our November update, where we’ll showcase the arrival and installation of our copper stills!*